So far each worker had a name and a speed. Many questions instead talk about groups: so many men, women or boys, working so many hours a day for so many days. The key idea here is that a job needs a fixed amount of labour, which we can count in man-days or man-hours. Change the number of workers, the hours or the days, and the product stays the same. This lesson also shows how to compare workers of different kinds by turning them all into one kind.
Man-days and man-hours
If men take days to finish a job, the job needs man-days of labour. Whatever the team, the same job needs the same man-days: men would take days, men would take days.
For the same job: . If hours per day also change: .
This is the inverse proportion between workers and time from the first lesson, written for groups.
Example 1
A certain number of men can complete a piece of work in days. If there were men more, the work could be finished in days less. How many men were there originally?
Let the original number of men be .
| Number of men | Days to finish |
|---|---|
The number of men is inversely proportional to the number of days, so the products are equal:
(The second line divides both sides by .) There were men originally.
Workers of different kinds
When men and boys (or men and women) work together, first find how many of one kind equal one of the other. Then turn the whole team into a single kind.
Example 2
If men or boys can finish a piece of work in days, in how many days can men and boys finish it?
" men or boys" means men do the same work as boys, so men boys. Then
So the team is boys.
| Number of boys | Days |
|---|---|
They finish it in days.
Example 3
men and women, working hours a day, finish a job in days. men and women, working hours a day, do the same job in days. In how many days will men alone, working hours a day, do it?
Count the total man-hours and woman-hours in each case.
Case (i): each day gives man-hours, so in days there are man-hours; likewise woman-hours.
Case (ii): man-hours and woman-hours.
It is the same job, so the two amounts of labour are equal. Writing for one man-hour and for one woman-hour:
So women do the work of men. The first team, men and women, is therefore worth men.
| Men | Hours per day | Days |
|---|---|---|
men working hours a day finish the job in days.
Earnings for groups
Example 4
men and boys together earn ₹252 in days, and men and boys together earn ₹624 in days. In what time will men and boys earn ₹1020?
Let one man earn ₹ a day and one boy ₹ a day.
Double (1): . Subtract this from (2): . Then , so .
A team of men and boys earns rupees a day. If they need days,
They take days.
When the team shrinks
Example 5
men are employed to do a piece of work which they could finish in days, but men leave at the end of every days. In what time will the work be completed?
The job needs man-days.
| Stage | Men | Days | Man-days | Work done |
|---|---|---|---|---|
| 1 | ||||
| 2 | ||||
| 3 | ? |
After two stages, man-days are done, leaving . Fifteen men need days for that, which is less than , so no one else leaves.
Total time days.
Practice
- men can finish a job in days. If more men join at the start, how many days will the job take?
- A group of men can finish a job in days. With more men, it would take days less. How many men are in the group?
- men or women can do a job in days. In how many days can men and women do it?
- men working hours a day finish a job in days. How many days will men working hours a day take?
- men and boy together earn ₹1100 in days, and men and boys earn ₹2400 in days. In how many days will men and boys earn ₹1760?
- men could finish a job in days, but men leave at the end of every days. In how many days is the job finished?
- men and women working hours a day finish a job in days. If man does the work of women, how many days will men working hours a day take?
Answers
Show answers
- , so days.
- , so and men.
- men women, so men women and the team is women. , so days.
- , so days.
- Daily: and . Then , so , giving and . The team earns a day, so days.
- The job needs man-days. First days: . Next days: . Left: , done by men in days. Total days.
- women man, so the team is men. , so days.