Curriculum
If a person A can finish a piece of work in n days, then A’s 1 day work is:
![]()
For example, if A can finish a work in 10 days, then A’s 1 day work is:
![]()
If A is twice as good as B, then A takes half the time taken by B to finish the same work.
In work problems, the number of men and the time taken are inversely proportional.
If 10 men take 20 hours to finish a work, and 20 men are used, then:
![]()
So,
![]()
Therefore, if the number of men increases, the time taken decreases.
The relation is:
![]()
If the number of men doing a work changes in the ratio 2 : 3, then the time taken changes in the inverse ratio:
![]()
Formula:
![]()
So,
![]()
This means men and time are inversely related.
A can do a piece of work in 12 days and B alone can do it in 15 days. We need to find how many days both will take together.
A’s 1 day work:
![]()
B’s 1 day work:
![]()
Together, A and B’s 1 day work:
![]()
Taking LCM 60:
![]()
So, both together complete
of the work in 1 day.
Therefore, total time taken:
![]()
So, A and B together can finish the work in 6⅔ days.
A and B together can do a piece of work in 12 days.
B and C together can do it in 15 days.
C and A together can do it in 20 days.
We need to find how many days A, B and C together can finish the work, and also separately.
Given:
![]()
![]()
![]()
Adding all three:
![]()
LCM is 60:
![]()
![]()
So,
![]()
Therefore, A, B and C together can finish the work in 10 days.
To find A alone:
![]()
![]()
LCM is 30:
![]()
So, A alone can finish the work in 30 days.
Similarly, B and C can also be found using the same method.
A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days, then A goes away. We need to find how many more days B will take to finish the work.
A’s 1 day work:
![]()
B’s 1 day work:
![]()
Together, their 1 day work:
![]()
LCM is 100:
![]()
In 5 days, A and B together complete:
![]()
Remaining work:
![]()
B’s 1 day work is:
![]()
So, B will complete
work in 11 days.
Therefore, B takes 11 more days.
A can do a piece of work in 12 days, while B alone can do it in 15 days. They work together for 5 days, then C finishes the rest of the work in 2 days. They are paid ₹960 for the whole work. We need to divide the money.
A’s 1 day work:
![]()
B’s 1 day work:
![]()
A and B together:
![]()
The slide uses the combined work idea:
![]()
Then,
![]()
![]()
The work ratio is:
![]()
LCM is 60:
![]()
Total ratio parts:
![]()
A’s share:
![]()
B’s share:
![]()
C’s share:
![]()
So, the money is divided as:
A = ₹400
B = ₹320
C = ₹240
A can do a piece of work in 10 days and B can do it in 15 days. A and B work together for 5 days. The rest of the work is finished by C in 2 days. They are paid ₹1920. We need to find how the money should be divided and their daily wages.
A’s 1 day work:
![]()
B’s 1 day work:
![]()
A and B together:
![]()
In 5 days, A and B complete:
![]()
Remaining work:
![]()
C completes
work in 2 days.
So, C’s 1 day work:
![]()
Work done by A in 5 days:
![]()
Work done by B in 5 days:
![]()
Work done by C in 2 days:
![]()
So, the work ratio is:
![]()
LCM is 6:
![]()
Total ratio parts:
![]()
A’s share:
![]()
B’s share:
![]()
C’s share:
![]()
Daily wages:
A works 5 days, so A’s daily wage:
![]()
B works 5 days, so B’s daily wage:
![]()
C works 2 days, so C’s daily wage:
![]()
Therefore:
A = ₹960, daily wage ₹192
B = ₹640, daily wage ₹128
C = ₹320, daily wage ₹160
A is thrice as good a workman as B and is therefore able to finish a piece of work 60 days less than B. We need to find the time in which they can do the work together.
Suppose B finishes the work in
days.
Since A is thrice as good as B, A takes one-third of B’s time.
So, time taken by A:
![]()
Given that A takes 60 days less than B:
![]()
Multiplying by 3:
![]()
![]()
![]()
So, B takes 90 days.
A takes:
![]()
A’s 1 day work:
![]()
B’s 1 day work:
![]()
Together:
![]()
So, A and B together can finish the work in:
![]()
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together, but A leaves the work after 2 days, and B leaves 3 days before the work is finished. We need to find the total time taken.
A’s 1 day work:
![]()
B’s 1 day work:
![]()
C’s 1 day work:
![]()
A, B and C work together for the first 2 days.
Their 1 day work:
![]()
LCM is 60:
![]()
In 2 days, they complete:
![]()
After that, A leaves.
B leaves 3 days before completion, so C alone works for the last 3 days.
C’s 3 days work:
![]()
Remaining work after the first 2 days and C’s final 3 days:
![]()
![]()
![]()
This
work is done by B and C together.
B and C’s 1 day work:
![]()
LCM is 60:
![]()
Time taken by B and C to complete
work:
![]()
![]()
So, total time:
A+B+C together = 2 days
B+C together = 2 days
C alone = 3 days
Total time = 7 days
A and B can do a piece of work in 45 days and 40 days respectively. They begin the work together, but A leaves after some days and B finishes the remaining work in 23 days. We need to find after how many days A left.
A’s 1 day work:
![]()
B’s 1 day work:
![]()
A and B together:
![]()
LCM is 360:
![]()
B’s 23 days work:
![]()
Remaining work done by A and B together:
![]()
Now, A and B together do
work in 1 day.
So, time taken to do
work:
![]()
![]()
![]()
Therefore, A left after 9 days.
A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues for 12 days. After that, A and C complete the remaining work in 48 days. We need to find how many days C alone will take.
A’s 1 day work:
![]()
B’s 1 day work:
![]()
A and B together:
![]()
LCM is 600:
![]()
In 20 days, A and B complete:
![]()
A’s 12 days work:
![]()
So far, work completed:
![]()
Remaining work:
![]()
This remaining
work is completed by A and C together in 48 days.
So, A and C’s 1 day work:
![]()
C’s 1 day work:
![]()
LCM is 240:
![]()
Therefore, C alone can finish the work in 240 days.
A and B together can do a piece of work in 12 days.
B and C together can do it in 15 days.
A is twice as good as C.
We need to find in how many days B alone can finish the work.
Given:
![]()
![]()
Since A is twice as good as C:
![]()
Let C’s 1 day work be:
![]()
Then A’s 1 day work is:
![]()
Now:
![]()
![]()
Subtracting:
![]()
![]()
But:
![]()
So:
![]()
![]()
Now B’s 1 day work:
![]()
LCM is 60:
![]()
Therefore, B alone can finish the work in 20 days.
A and B working alone can finish a piece of work in 8 days and 7 days respectively. They work alternately for a day each, starting with A. We need to find how many days the work will be finished.
A’s 1 day work:
![]()
B’s 1 day work:
![]()
In 2 days, A and B together complete:
![]()
LCM is 56:
![]()
In the first 6 days, there are 3 such cycles.
Work done in 6 days:
![]()
On the 7th day, it is A’s turn.
A does:
![]()
Total work done by the end of 7 days:
![]()
Remaining work:
![]()
Now it is B’s turn.
B’s 1 day work:
![]()
To complete
work, B needs:
![]()
Therefore, total time:
![]()
A certain number of men complete a piece of work in 60 days. If there were 8 more men, the work would be finished in 10 days less, that is, in 50 days. We need to find the original number of men.
Let the original number of men be:
![]()
Original work:
![]()
With 8 more men:
![]()
Since work is the same:
![]()
![]()
![]()
![]()
Therefore, the original number of men is 40.
4 men or 6 boys can finish a piece of work in 20 days. We need to find how many days 6 men and 11 boys can finish it.
Given:
![]()
So,
![]()
Therefore:
![]()
Now, 6 men and 11 boys together are equivalent to:
![]()
If 6 boys can finish the work in 20 days, then total work:
![]()
With 20 boys, time taken:
![]()
Therefore, 6 men and 11 boys can finish the work in 6 days.
2 men and 3 women working 7 hours a day finish a work in 5 days.
4 men and 4 women working 3 hours a day finish the same work in 7 days.
We need to find the number of days required for 7 men only, working 4 hours a day, to finish the work.
Let 1 man’s 1 hour work be:
![]()
Let 1 woman’s 1 hour work be:
![]()
First condition:
![]()
![]()
Second condition:
![]()
![]()
Both are equal because the work is same:
![]()
![]()
![]()
So,
![]()
The total work can be converted in terms of men’s work.
Using the first condition:
![]()
Since:
![]()
Then:
![]()
So:
![]()
Total work:
![]()
Now, 7 men working 4 hours per day do:
![]()
Number of days:
![]()
Therefore, 7 men working 4 hours per day can finish the work in 5 days.
2 men with 3 boys can earn ₹252 in 7 days.
4 men with 7 boys can earn ₹624 in 8 days.
We need to find in what time 6 men with 8 boys can earn ₹1020.
Let 1 man’s 1 day earning be:
![]()
Let 1 boy’s 1 day earning be:
![]()
From the first condition:
![]()
![]()
Equation 1:
![]()
From the second condition:
![]()
![]()
Equation 2:
![]()
Multiplying Equation 1 by 2:
![]()
Equation 2:
![]()
Subtracting:
![]()
Substitute in Equation 1:
![]()
![]()
![]()
![]()
So, 1 man earns ₹9 per day and 1 boy earns ₹6 per day.
Earning of 6 men and 8 boys per day:
![]()
![]()
![]()
Time required to earn ₹1020:
![]()
Therefore, 6 men and 8 boys earn ₹1020 in 10 days.
25 men are employed to do a piece of work which they could finish in 20 days, but the men drop off by 5 at the end of every 10 days. We need to find in what time the work will be completed.
Total work:
![]()
First 10 days:
![]()
So, half the work is completed.
Remaining work:
![]()
After 10 days, 5 men leave, so remaining men:
![]()
Next 10 days:
![]()
Remaining work:
![]()
After another 10 days, 5 more men leave, so remaining men:
![]()
Time taken by 15 men to complete 50 man-days:
![]()
Total time:
![]()
Therefore, the work will be completed in 23⅓ days.
A can do half as much again as B can do in the same time. B alone can do a piece of work in 18 days. We need to find in how many days both together can finish the work.
“Half as much again as B” means A’s work is:
![]()
So, the ratio of work done by A and B is:
![]()
Therefore, the ratio of time taken is inverse:
![]()
B alone takes 18 days.
Since B corresponds to 3 parts:
![]()
![]()
A corresponds to 2 parts:
![]()
So, A alone can finish the work in 12 days.
A’s 1 day work:
![]()
B’s 1 day work:
![]()
Together:
![]()
LCM is 36:
![]()
So, time taken together:
![]()
Therefore, A and B together can finish the work in 7⅕ days.